合肥地铁7、8号线迎来新进展!

7月16日,7号线一期

石门路站至耕耘路站区间文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

左线顺利贯通文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

为该线贯通的第6条盾构单线区间合肥地铁7、8号线迎来新进展!文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

“石耕”区间盾构机出石门路站后沿始信路中敷设,至耕耘路站接收。区间全长1014米,线间距为15米,隧道覆土约12米至14米。该区间隧道侧穿多个建构筑物,盾构掘进干扰较多,对监测量测精度要求高。文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

为保障区间顺利贯通,合肥轨道集团梳理盾构出土制约因素,制定专项解决方案,加强沟通协调,保障盾构施工连续性,降低掘进安全风险。同时,加强盾构掘进过程监测,严格控制盾构掘进参数和掘进姿态,确保盾构隧道成型质量和地面建筑物安全,顺利实现区间贯通。文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

截至目前文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

7号线一期16座车站文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

已有7座主体结构封顶文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

31条盾构单线区间已有6条贯通文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

轨道交通8号线合肥地铁7、8号线迎来新进展!文章源自三百米生活-https://www.300m-team.com/banshizhinan/jiaotongchuxing/60075.html

7月15日下午,

8号线一期梅冲湖路站

主体结构顺利封顶,

为该线第6座主体结构封顶的车站。

截至目前,

8号线一期12座车站

已有6座主体结构封顶,

24条盾构单线区间已有3条贯通。合肥地铁7、8号线迎来新进展!

梅冲湖路站位于蒙城北路与梅冲湖路交叉口,沿蒙城北路南北向设置,为明挖地下二层单柱双跨岛式车站,车站设4个出入口、2组风亭,车站主体总长207米,开挖深度约17.5米,主体结构采用明挖顺作法施工。该车站地下岩层较浅,基坑开挖难度大,周边住宅小区、学校、医院多,对于施工噪声控制要求高。合肥地铁7、8号线迎来新进展!

为确保车站顺利实现主体结构封顶,合肥轨道集团精准施策,一方面加大机械设备的投入和使用,针对基坑开挖4米即见岩层的难题,投入2台破碎锤挖机在可施工时段内不间断对石方进行破除,确保基坑全部见底任务顺利完成;另一方面,合肥轨道集团合理筹划安排施工工序,在夜间时段组织钢筋绑扎、防水铺设等无噪声工作,在确保噪声不扰民的基础上保障工时利用效率最大化,最终顺利实现梅冲湖路站主体结构封顶。